Project Overview

Complex refurbishment and redevelopment of Twyford Abbey, involving retention of the existing historic façade while enabling complete internal reconstruction.

Key Structural Challenges

  • Preserving the existing historic façade while demolishing everything behind it
  • Providing lateral stability to retained walls during floor and roof removal
  • Designing backpropping that worked with existing floor conditions
  • Working within heritage constraints on a listed structure

Our Solution

We designed a carefully sequenced temporary works package:

  • Backpropping of existing RC floors to enable safe demolition equipment operation above
  • Façade retention system designed to restrain the historic elevation independently
  • Lateral propping of existing walls to maintain stability during floor and roof demolition
  • Detailed methodology defining the construction sequence and hold points

Outcome

The temporary works scheme was successfully implemented, preserving the historic façade intact throughout the structural demolition and reconstruction phases.